How much do solar panels for data centres cost?
Real UK costs by system size, sub-vertical, and financing route. Updated for 2026.
What does data centre solar PV actually cost in the UK?
The direct answer: a rooftop solar PV installation on a UK data centre building costs between £700 and £1,250 per kilowatt of installed capacity, all-in, for a system delivered to MCS commercial standards with Tier III/IV operational continuity throughout installation. For the most common data centre system sizes — 250 kW to 2 MW — that translates to a total project cost of £175,000 to £2.5 million. The wide range is driven by roof type, access difficulty, electrical infrastructure available, DNO connection process, and the specific continuity design required for your facility tier.
This guide gives you real UK pricing benchmarks for 2026, broken down by data centre sub-type, and explains the factors that drive variation. This page does not give a single number because the honest answer is that a hyperscale campus in Slough and an enterprise data room in Nottingham have very different cost profiles. Use this guide to form a realistic budget before commissioning a formal feasibility study — and to sense-check any quotes you receive.
Cost per kW by system size
Data centre solar costs follow the same economies of scale as all commercial solar:
| System size | Cost per kW | Typical data centre type | Typical total cost |
|---|---|---|---|
| 50–100 kW | £1,050–£1,250/kW | Small enterprise data room, edge/telco POP | £52,000–£125,000 |
| 100–500 kW | £850–£1,050/kW | Medium colocation, enterprise data centre | £85,000–£525,000 |
| 500 kW–2 MW | £750–£900/kW | Large colocation, cloud provider campus | £375,000–£1.8m |
| 2 MW+ | £700–£800/kW | Hyperscale campus, multi-building rollout | £1.4m–£8m+ |
All figures are ex-VAT, all-in (design, equipment, labour, scaffold/MEWP, G98/G99 DNO connection, commissioning, Scope 2 evidence pack). Updated for 2026 pricing. Regional contractor costs vary by up to ±10%.
What drives cost variation in data centre solar?
Two identical-capacity systems on two different data centre buildings can have costs varying by 30–40%. The main drivers:
1. Roof type and condition
Modern flat EDPM or profiled steel roofing (post-2005 construction) is the cheapest to work with: ballasted or mechanically fixed racking, no special weatherproofing requirements, and good structural loading capacity. Older data centres — particularly converted industrial buildings from the 1980s–90s — may have asbestos cement sheeting (ACM) that cannot carry PV directly and requires a combined re-roof programme. An ACM re-roof adds £30–£80/m² to the project cost, but the PV business case often covers most or all of this additional outlay within the payback period.
2. Electrical infrastructure
Most data centres have primary 11 kV or 33 kV supplies with modern secondary LV switchgear. The inverter connection point — typically a dedicated incomer to the LV main distribution board — needs assessment for available bus capacity. Some facilities have modular or pre-manufactured switchgear that requires factory-modified busbars; others have abundant spare incomer positions. The difference in electrical installation cost between a simple connection and a complex switchboard modification can be £15,000–£60,000 on a large system.
3. Tier III/IV continuity design overhead
Installing solar on a live Tier III or Tier IV data centre requires phased installation sequences, UPS transfer testing at each phase, anti-islanding relay specification and commissioning, and additional project management overhead compared to a simple commercial install. This adds approximately 8–15% to the labour and design cost versus an equivalent-capacity installation on a non-critical commercial building. It is non-negotiable — it is the cost of doing the installation correctly on mission-critical infrastructure.
4. Access difficulty
Rooftop access on data centre buildings is often more complex than on standard commercial or industrial roofs. Security perimeters require personnel vetting and escorted access. Cooling plant — CRAC units, cooling towers, chillers — occupies significant roof area and restricts working zones. Height, parapet design, and MEWP access (mobile elevated work platform) requirements vary by building. Access overhead typically adds £8,000–£25,000 to a large data centre install compared to an open industrial roof.
5. DNO grid connection
Solar PV for data centres is invariably designed as a zero-export, fully self-consumed system. This means the DNO does not need to assess reverse power flow on the local distribution network — the solar generation is completely absorbed into the building's IT load. For systems below 50 kW, G98 self-certification applies (no DNO charge). For systems 50 kW–1 MW, a G99 application is required. The DNO technical study and connection agreement cost between £500 and £8,000 depending on the DNO and the complexity of the technical study. A good installer submits G99 applications immediately after the site survey to start the clock, since the connection process is usually the longest item in the project timeline (65 working days statutory minimum for the technical study).
6. Location
Contractor labour costs vary by approximately ±10% across the UK. London and the South East are typically at the top of the range; the Midlands and Wales are at the lower end. For data centre solar in Slough or London Docklands, you should budget at the upper end of the cost-per-kW ranges above. For facilities in Manchester, Birmingham, or Cardiff, expect to come in at the lower end or below mid-range.
Financing options — how most data centre operators fund solar
Data centre solar is usually paid for in one of three ways, and the true cost depends on which you use. None of them is a grant: grants and funding sets out why.
Cash purchase (the Annual Investment Allowance)
For UK companies paying corporation tax at 25%, the £1m Annual Investment Allowance lets 100% of qualifying spend up to £1m be deducted from taxable profits in year one; above £1m, solar is special-rate plant, so the 50% first-year allowance applies, then 6% a year. On a £500,000 installation the AIA is a £125,000 tax saving, reducing the effective net cost to £375,000. At that net cost, against £100,000/year electricity savings, payback falls to 3.75 years rather than 5 years. Cash purchase usually gives the best long-run return where a company has the capital and a tax liability to use the relief; the mechanics are explained in Annual Investment Allowance for data centre solar.
Asset finance (hire purchase or finance lease)
Asset finance spreads the capital cost over several years, so repayments can be set against the electricity saving as it accrues. Under hire purchase the buyer is treated as owning the plant for capital allowances (CAA 2001 s67), so the AIA or first-year allowance stays with the operator; under a lease, who claims depends on the lease type. Rates and terms depend on the lender and the borrower, so compare written offers. This site does not arrange finance.
Power Purchase Agreement (PPA)
A PPA involves no capital outlay. A third-party funder (the PPA provider) owns, installs, insures and maintains the solar system, and you buy the generated electricity at an agreed price per kWh, usually set below the grid retail price, over a long contract term. Because the provider incurs the cost and owns the plant, it claims the capital allowances, not you (CAA 2001 s11). At the end of the contract the system may be bought out or the contract extended, depending on its terms.
PPAs return less to the host than cash purchase over the life of the system (the provider keeps part of the long-term value), but need no capital and move the technical risk to the funder. Operators that prioritise balance sheet efficiency over long-term yield often prefer them, and many pair on-site PV with an off-site corporate PPA for the rest of their load.
See our grants and funding page for detail on how capital allowances interact with these financing structures. The Industrial Energy Transformation Fund is closed: its last window closed on 19 April 2024, and GOV.UK confirmed in July 2025 that it will not be extended and has no successor.
Payback benchmarks: illustrative modelled ranges (2026)
These are illustrative ranges from a desk model, not results from completed projects. Treat them as a starting point for questions to put to installers:
| Location | Facility type | System | Annual saving | Payback |
|---|---|---|---|---|
| Slough | Colocation | 750 kW | £156,000 | 5.9 years |
| London | Colocation | 420 kW | £96,000 | 5.4 years |
| Manchester | Enterprise | 380 kW | £70,000 | 6.1 years |
| Cambridge | HPC / AI | 450 kW | £92,000 | 5.7 years |
| Crawley | Edge / telco | 420 kW | £93,000 | 5.1 years |
| Birmingham | Enterprise | 490 kW | £90,000 | 5.8 years |
Payback figures assume 100% self-consumption (typical for 24/7 IT load), 22–26p/kWh blended grid rate, no export income. Net cost after Annual Investment Allowance relief not applied (apply a 25% reduction to payback years for corporation tax payers using the Annual Investment Allowance).
Building in Scotland, Wales or Northern Ireland
The same array yields differently by nation. PVGIS 5.3, for a flat roof tilted 10 degrees facing south, models 946 kWh per kWp a year in Cardiff, 828 in Belfast, 805 in Edinburgh and 772 in Glasgow, so a Glasgow roof generates about 18% less than a Cardiff one and the cost per kWh generated rises in the north. Scottish sites yield 772-805 kWh per kWp on a flat roof, against 946 in Cardiff; Welsh sites sit close to the South East. On-site renewables are excluded from business rates in Scotland and Wales until 2035, while in Northern Ireland plant over 50 kW is rateable. Scotland needs a Transmission Impact Assessment above 200 kW on the mainland, and Northern Ireland uses NIE Networks' G99/NI. Export is paid under the SEG in Great Britain and at supplier-set tariffs in Northern Ireland; the Northern Ireland funding and grid rules are on the grants page.
Cost ranges by sub-vertical
Hyperscale Data Centres
- Typical system
- 1–5 MW (rooftop) + ground-mount potential to 10+ MW
- Project value
- £700,000–£8m+
- Payback
- 7 years
- Annual generation
- 920,000–10m+ kWh
Colocation Data Centres
- Typical system
- 300 kW–3 MW
- Project value
- £210,000–£2.4m
- Payback
- 6.5 years
- Annual generation
- 275,000–2.75m kWh
Edge Data Centres / Telco POPs
- Typical system
- 50–300 kW
- Project value
- £45,000–£270,000
- Payback
- 7 years
- Annual generation
- 46,000–275,000 kWh
Enterprise / On-Premise Data Centres
- Typical system
- 100 kW–1 MW
- Project value
- £90,000–£800,000
- Payback
- 6.5 years
- Annual generation
- 92,000–920,000 kWh
Cloud Provider Data Centres
- Typical system
- 500 kW–5 MW
- Project value
- £350,000–£4m+
- Payback
- 6.8 years
- Annual generation
- 460,000–4.6m kWh
HPC and AI Data Centres
- Typical system
- 800 kW–8 MW
- Project value
- £560,000–£6.4m+
- Payback
- 6.3 years
- Annual generation
- 736,000–7.4m kWh
Send an enquiry about your site
Four short steps. This site is a publisher, not an installer. We read every enquiry and reply by email.
Cost questions
How much do solar panels for a data centre cost in the UK?
Hyperscale and large colo (1–5 MW): £700k–£8m+. Mid-colo (300 kW–3 MW): £210k–£2.4m. Edge (50–300 kW): £45k–£270k. Cost per kW typically £700–£900 above 1 MW, £750–£950 for 300 kW–1 MW range. Capital allowances cover 75–85% of effective net cost.