Data Centres in Scotland: Operating Sites, Pipeline and Planning Rules
What is built, what is proposed, how the September 2026 planning changes work, and what a rooftop array yields north of the border.
Scotland has 15 operating data centres and 24 major proposals in the planning system, together at least 6,000 MW, according to a September 2026 analysis reported by Resultsense citing The Scotsman; the largest operating facility it names is 12 MW, in Lanarkshire. Our own list, checked on each operator's website on 3 November 2026, has 9 operating Scottish sites from five operators. Since 17 September 2026 any new Scottish data centre with a power capacity above 50 MW needs an environmental impact assessment, and on 16 September the Scottish Parliament resolved that no planning decisions on hyperscale applications should be made until national guidance is in place.
What is operating and what is only proposed?
The gap between the two is the story. Fifteen operating facilities, the biggest of them 12 MW on The Scotsman's count, sit beside proposals measured in hundreds of megawatts. The proposals are applications, not capacity: several have no published size, some have already fallen away, and none can be counted as supply until they are consented, connected and built.
| Proposal (reported) | Area | Size (MW) |
|---|---|---|
| Blackdog | Near Aberdeen | 600 |
| Auchtertool | Fife | 600 |
| Two Ravenscraig schemes | North Lanarkshire | 1,050 combined |
| Two Chapelhall schemes | North Lanarkshire | 1,000 combined |
| Hurlford | East Ayrshire | 540 |
Source: Resultsense, 8 September 2026, citing The Scotsman, re-read on 3 November 2026. The article calls the 6,000 MW total a floor. Verify individual schemes against the planning authority's register.
Operating data centres in Scotland: the sourced list
These are the Scottish sites we could confirm as operating on the operator's own website. A figure appears in the power column only where the operator labels it IT load. Two larger sites publish power figures of another kind: DataVita says its DV1 site at Chapelhall has "40MW of power", and the University of Edinburgh says the Advanced Computing Facility's capacity "was upgraded from 8MW to 38MW in 2023". The list is the same source of truth as Scotland on the UK data centre map, and the companies are profiled on UK data centre operators.
| Facility | Operator | Town | IT power the operator states | Source (checked 3 November 2026) |
|---|---|---|---|---|
| Aberdeen Data Centre | brightsolid | Aberdeen | — | operator page |
| DV1 Data Centre, Lanarkshire | DataVita | Chapelhall | — | operator page |
| Dundee HQ and Data Centre | brightsolid | Dundee | — | operator page |
| Advanced Computing Facility (ACF) | University of Edinburgh (EPCC) | Easter Bush | — | operator page |
| Edinburgh SC-2 (Medway) | Pulsant | Edinburgh | 2.16 MW | operator page |
| Edinburgh South Gyle SC-1 | Pulsant | Edinburgh | 3.4 MW | operator page |
| DV2 Data Centre, Glasgow | DataVita | Glasgow | — | operator page |
| Glasgow Data Centre (DC1) | iomart | Glasgow | — | operator page |
| Edinburgh SC-3 (Newbridge) | Pulsant | Newbridge | 1.3 MW | operator page |
The planning rules changed in September 2026
- National Planning Framework 4: "Green data centres" are a class of development within National Development 12, the Digital Fibre Network, which applies to schemes of a scale that would otherwise be major development (NPF4, Annex B). The framework does not define "green data centre" in detail.
- Notification and environmental impact assessment: a Notification Direction in force from 17 August 2026 requires planning authorities to notify Scottish Ministers of data centre applications above 50 MW (Scottish Government). A further Direction from the Chief Planner, dated 16 September 2026 and in force from 17 September 2026, requires an EIA for any new data centre whose total electrical power capacity exceeds 50 MW; smaller schemes are still screened case by case (Scottish Government).
- Hyperscale pause: on 16 September 2026 the Scottish Parliament agreed motion S7M-01177, as amended, by 80 votes to 26 with 15 abstentions. It says no planning or consenting decisions on hyperscale applications should be made until national planning guidance is complete, asks ministers to report back by the end of 2026, and to publish the guidance within 12 months (Minutes of Proceedings). It is a parliamentary resolution, not law. On 8 October the minister wrote that the guidance would be published "before Christmas" (letter to the Climate Action Committee); none had been published when we checked on 3 November 2026.
The Lanarkshire AI Growth Zone
The UK Government named Lanarkshire as an AI Growth Zone on 29 January 2026, delivered by DataVita around its Airdrie site with CoreWeave. The announcement says DataVita plans "more than 500MW of on-site power" within four years, which is generating capacity, not data centre IT load (GOV.UK). DataVita describes its estate as five sites, two live and three in development, all in the central belt. The September 2026 EIA Direction applies to any new data centre above 50 MW. The five zones and what government has published for each are on our AI Growth Zones page.
Where Scotland's data centres sit on the grid
Two distribution network operators cover Scotland. SP Energy Networks serves the central belt and the south of Scotland, about 2 million customers (Ofgem), which is where Edinburgh, Glasgow and the Lanarkshire sites connect. SSEN Distribution serves the north, including the Highlands and islands, with 797,655 customers in 2024/25 (SSEN); the Aberdeen and Dundee sites are on its network. Transmission is owned by SP Transmission in the centre and south and SSEN Transmission in the north.
The rule that matters most for a large roof is the Transmission Impact Assessment. In Scotland a generator needs one above 200 kW on the mainland and 50 kW on the islands; the rise to 5 MW that took effect in England and Wales in May 2025 (CMP446) does not apply here (NESO). A data-centre-scale array will usually be above 200 kW, so plan for the assessment alongside the distribution application; the steps are on G99 and grid connection for data centres.
Generation is not the constraint. 73.1% of the electricity generated in Scotland in 2024 was renewable, 37.9 TWh (Scottish Government energy statistics). Scottish solar PV capacity reached 698 MW at the end of 2024 (Climate Change Plan monitoring report), and DESNZ reports that Scottish solar generation rose 48% in 2025, the highest growth of the UK nations (DESNZ, regional renewable electricity in 2025). The delay in most proposals is moving power to where the campuses are.
Five Scottish rules that change a rooftop solar project
| Rule | What it says | What it means on a data-centre roof | Source |
|---|---|---|---|
| Business rates | Plant on non-domestic property that generates or stores power from wholly or mainly renewable sources, including storage batteries, is excluded from rates valuation from 1 April 2023 to 31 March 2035. | Adding rooftop PV or a battery does not raise the rateable value for that plant until 2035. | SSI 2023/32 |
| Permitted development (Class 6J) | Solar on non-domestic buildings has no kW cap, provided panels protrude no more than 1 m. Not on listed buildings or their curtilage; limits on principal and road-facing elevations in conservation areas; excluded within 3 km of an aerodrome or technical site and in certain protected areas. Free-standing solar (Class 6N) is capped at 12 m². | A large flat-roof array on an unlisted building outside those zones can often proceed without a planning application; ground-mount needs permission. | GPDO (Scotland) Part 1B |
| Transmission Impact Assessment | Required above 200 kW on mainland Scotland and 50 kW on the islands. | Most data-centre arrays cross the threshold; build the assessment into the programme. | NESO |
| Smart Export Guarantee | Applies across Great Britain, including Scotland, for installations up to 5 MW; tariffs must be above zero. | Export income exists, but a flat 24/7 load exports little, so it is a minor line. | Ofgem |
| Section 63 action plans | Scotland has no minimum energy efficiency standard for letting. Non-domestic buildings over 1,000 m² that are sold or newly let need an Action Plan, with exclusions for buildings built to 2002 or later standards and Green Deal properties. | For a colocation landlord, on-site generation can form part of the action plan's improvement measures. | SSI 2016/146 |
What Scotland means for on-site solar
Rooftop yield is lower in Scotland than in southern England. PVGIS 5.3 (EU Joint Research Centre, SARAH3 radiation data, 14% losses) models a flat roof tilted 10 degrees facing south at 805 kWh per kWp a year in Edinburgh, 772 in Glasgow, 791 in Aberdeen and 734 in Inverness (Edinburgh query), and 787 in North Lanarkshire, against 932 at Slough. At the optimal tilt the same four cities give 908, 855, 900 and 813. Welsh roofs do better: Cardiff models 946, so the same array in Edinburgh or Glasgow produces about 15-18% less; see data centres in Wales.
Because a data centre's load is flat and continuous, nearly all of the output is still self-consumed and avoids imported power, so the case turns on roof area, structure and import price rather than export income.
Funding in Scotland, honestly
No grant funds data-centre solar in Scotland today. Business Energy Scotland's SME Loan is open but "not accepting new applications for solar PV projects" and pays no cashback on batteries (Business Energy Scotland). The Scottish Industrial Energy Transformation Fund is closed, its last call having closed in March 2025, and it never funded solar PV (Scottish Government). What applies is UK-wide capital allowances (solar is special-rate plant: the £1m Annual Investment Allowance, then the 50%% first-year allowance), the rates exclusion above and the Smart Export Guarantee. The routes are compared on what does and does not fund data-centre solar in Scotland.
Panels on an existing building are a different route from the new-build hyperscale schemes above: they are not a new data centre application, but structure, fire safety and grid-connection requirements still apply. Sizes and costs are on data centre solar costs, and the city pages for Edinburgh and Glasgow cover rooftop detail. For every other region, see the full UK data centres map and list.
Frequently asked questions
How many data centres are there in Scotland?
A September 2026 analysis reported by Resultsense, citing The Scotsman, counts 15 operating data centres in Scotland, the largest 12 MW in Lanarkshire, with 24 major proposals totalling at least 6,000 MW. Our own list, checked on operator websites on 3 November 2026, confirms 9 operating sites, in Edinburgh, Glasgow, Lanarkshire, Aberdeen, Dundee and Easter Bush. There is no official register.
What did the Scottish Government change for data centres in 2026?
A Notification Direction from 17 August 2026 requires councils to notify Scottish Ministers of data centre applications above 50 MW, and a Chief Planner Direction in force from 17 September 2026 requires an environmental impact assessment for any new data centre with a power capacity above 50 MW. Smaller schemes are still screened case by case.
Is there a pause on data centres in Scotland?
On 16 September 2026 the Scottish Parliament agreed a motion that no planning or consenting decisions on hyperscale data centre applications should be made until national planning guidance is complete. It is a resolution, not law. The minister said in October that the guidance would be published before Christmas.
How much does a solar panel produce in Scotland compared with Slough?
PVGIS 5.3 models a south-facing flat roof tilted 10 degrees with 14% losses at 805 kWh per kWp a year in Edinburgh, 772 in Glasgow, 791 in Aberdeen and 734 in Inverness, against 932 at Slough: roughly 14% to 21% less.
Who are the network operators for Scottish data centres?
SP Energy Networks serves the central belt and south of Scotland and SSEN Distribution the north, including the Highlands and islands. Transmission is owned by SP Transmission and SSEN Transmission.
Do rooftop solar panels on a Scottish data centre pay business rates?
No, not for the plant itself until 2035. SSI 2023/32 excludes plant on non-domestic property that generates or stores power from wholly or mainly renewable sources, including storage batteries, from rates valuation from 1 April 2023 to 31 March 2035.
Is a large rooftop array permitted development in Scotland?
Often. Class 6J of the Scottish permitted development order allows solar on non-domestic buildings with no kW cap if panels protrude no more than 1 m. It does not apply to listed buildings or their curtilage, is limited on some elevations in conservation areas, and is excluded within 3 km of an aerodrome or technical site and in certain protected areas.
When does a Scottish rooftop array need a Transmission Impact Assessment?
Above 200 kW on mainland Scotland and above 50 kW on the Scottish islands. The 5 MW threshold that applies in England and Wales since May 2025 does not apply in Scotland, so most data-centre-scale arrays will need one.
Pricing solar for a Scottish data centre roof?
Four short steps. This site is a publisher, not an installer. We read every enquiry and reply by email.